![]() When a Finish-to-Finish predecessor is used to connect two tasks, this means that both tasks finish at the same time. However, these tasks can begin at different points in time. The image below shows an example of a Start-to-Start type of predecessor. When a Start-to-Start predecessor is used to connect two tasks, this means that both tasks start at the same time. However, these tasks can finish at different points in time. The image below shows an example of a Finish-to-Start type of predecessor. When a Finish-to-Start predecessor is used to connect two tasks, this means that Task B cannot start before Task A is finished. Inspire Planner supports the four (4) common types of dependencies:įinish-to-Start predecessors are the most commonly used type of dependency. ![]()